2023 Capital Improvement Projects

Street and Sidewalk Projects

Cracksealing-West "half" of city: COMPLETE

Sidewalk Replacements (Dougherty Ridge): UNDERWAY

Greenbriar Estates Cul-de-sac Reconstruction  UNDERWAY

Bent Brook Road Slab Replacements  UNDER CONTRACT

Street Resurfacing (Apple Hill and part of Harwood Hills) UNDER CONTRACT

Microsurfacing (Old Dougherty Ferry, Bellerosa, Westmark, Movie, Sateen, and part of Highland) UNDER CONTRACT

Manchester Road Improvements  (MoDOT project: 2022-2024)


Future Major Projects

(Federal grants)

Des Peres Road Roundabout  New grant awarded, tentative 2024 construction
Lindemann Road Resurfacing (2024 Construction)



Facility

Building Improvements and New Building-Design underway, Construction starting in mid-2023


Equipment


Replace 3/4T pickup DELIVERED AND IN-USE

Replace 2T dump truck: CURRENTLY AT UPFITTER

Replace Bobcat skid-steer: DELIVERED AND IN-USE

Replace Asphalt Roller: DELIVERED AND IN-USE

Replace Air Compressor: ORDERED

Replace Wood Chipper: DELIVERED AND IN-USE

Last updated 6/1/23


Manchester Corridor Study (East of Ballas)


 This study started in 2016 and was completed in 2017.  Presentations were given to the Board of Aldermen during a work session and to the Planning & Zoning Commission during a regular meeting.  Having this study in place put the City in an excellent position to compete for federal project funding in the future, and provides a template to both MoDOT and developers. In 2018, the City was awarded a grant to complete pedestrian upgrades in conjunction with MoDOT's planned 2022 reconstruction of Manchester Road.
Final Report

Presentations Slides


Street Repairs Coming Soon